I have two resources. One is a person and the other is an instrument.
The person has manual tasks that he does by himself.
The instrument runs by itself to complete an automated task.
And: The instrument has to be cleaned by the person.
When it is being cleaned, both the instrument and the person are 100% busy. It takes 15 minutes to clean the instrument. How can I set this up so that if an instrument and a person are both assigned, they are both 100% busy and the duration doesn’t change?