Is it possible to defer a task until another task, in a separate project, is completed?

It’s getting it to work across projects that I’m struggling with specifically.

I’ve tried looking through the forums but haven’t found this issue come up before, which makes me think I may be missing something obvious!

Thanks,
Matt

Unfortunately it’s not possible to affect a task’s availability based upon the status of a task in another project. Many users create “meta” tasks within the parent project that have a link to the other project.

Ah, I see, thank you for clearing that up.

It’s a shame, it seems cross-dependencies like this, between projects, would be fairly common. Unless I’m missing a philosophy in approaching this perhaps.

Thanks for the tip about linked meta tasks though, I’ll look into that and otherwise hope for a feature addition later.