Display estimated time duration

Is there a way to display the estimated time duration for tasks? I’ve seen discussions about how much people want to show/compute durations for groups of tasks. But I just want to SEE the field!

You can find its setting in Layout tab at preference (in OmniFocus menu [⌘ + ,] ).
You can turn checkbox to enable estimated time duration field .

1 Like

thanks, this helps, BUT…

that’s only when I display in column mode, which I find far less useful than “fluid” mode. Is there a way to show these data in “fluid” mode?

And, is there any way to show these data on IOS OF?

1 Like

The only way to see estimated durations in OmniFocus on iOS is using the inspector.

If you haven’t already, I encourage you to email the Omni Group at omnifocus@omnigroup.com to request an option to display estimated durations in fluid mode (Mac) and in the outline view on iOS.

1 Like

This topic was automatically closed 30 days after the last reply. New replies are no longer allowed.