Don't see tasks with no context by sequentiell project

Helllo forum

I create a project with some tasks.
The project is sequentiell.
Some tasks don’t have a context.
I don’t see this tasks in context view.
When I change the project to parallel I see this tasks in context view.

What is the idea behind this to don’t see this tasks in sequentiell project?

Regards

Jochen

Hi Jochen,

Check to make sure that the View settings for the Contexts perspective are set to “Remaining”. By design, only the first incomplete action in a sequential project is available, so only one action will show up when View is set to “Available”.

Cheers,
Tim

2 Likes

@Tim

Thanks for quick and helpful feedback.
I will show it later.

Jochen

2 Likes