Hiding deferred tasks

Is there a way to defer a task in the future so that it does not visible in the project until the due date? I don’t want to see deferred tasks until they are due.

Using the button View in the toolbar you can choose to show only available tasks in Projects.

2 Likes

If you’ve given the project a due date, then this becomes the default due date for all of the actions. if you don’t want an action to become available until the day the project is due, set the defer date to the same date as the project’s due date. If the project’s due date changes you would need to manually update this defer date.