How to see total project duration in Omniplan?

This must be just me being dumb - but for the life of me I cannot see what I consider to be the most important concept of a project plan in Omniplan - the total project duration. I can see the project start and end dates, but I cannot see a duration. How do I get this information?

@pwnell Sorry for the trouble! It actually isn’t possible to display the project duration in the project window in the current version of OmniPlan for Mac. If you add the the project to a Dashboard the project duration will be visible there, or, if you’d like to work around this in the project window, you could create a top-level group task.

Yeah that is what I ended up doing - a top level group, thanks!

1 Like