How to set a “start finish + 2 days” in Omniplan

For example, “sf + 2”, “fs + 1”, …
Ask for help, thx.

FS+1D FF+1D and so on, where D is Day, H is hour etc

i want to ask for how to set, just like ms project…

Go to the column headers, right-click and choose “Prerequisites” (equivalent to MS Project “Predecessors”

Use the form I gave before to enter the information.

Does that help?

@Bowyee As @Nick describes, you can set this type of dependency up by entering values in the Prerequisites (or Dependents) outline column. Alternatively, you can enter the lead/lag value in the Task Dependencies Inspector. More information about this workflow is available in this section of OmniPlan’s manual: https://support.omnigroup.com/documentation/omniplan/mac/3.7/en/using-the-inspectors/#scheduling-tasks