How To Show Resource Days Off

I’m new to OmniPlan and was wondering if it is possible to factor in days that a resource is unavailable. I have resources that sometimes can only work half time so list them as two resources (Bob 100% and Bob 50%) but not sure how to factor in (Bob 50%) can’t work Tuesday and Friday next week.

Any help would be appreciated!

Thanks, Richard

Got the answer from Awesome Omni Support. In calendar view “select the resource”, choose “Extra & Off Hours” and shift-click and drag.

2 Likes

Watch the new OP videos for a good look at the main features. Tehre are four or five of them, and they only take a couple of minutes each. They’re pretty fun, too.