Hi,
new to Omniplan
I just want the duration to be based on the actual calendar days instead of working days.
And that it also counts the weekends into the duration.
Any advice?
Hi,
new to Omniplan
I just want the duration to be based on the actual calendar days instead of working days.
And that it also counts the weekends into the duration.
Any advice?
@Sketch This article on our Support site walks through setting up “elapsed time” durations in OmniPlan:https://support.omnigroup.com/op-lead-lag-time/
Hope this helps!