Indented Actions Are Always Sequential And Don't Respect Project Type

Hello, when I tag indented sub-tasks in a project, even when that project is set to “Parallel” or “Single Actions,” the indented tasks are always sequential. To reproduce, make a project with multiple tasks, then indent some of them, then tag with mixed tags: Only the first item at that level of childhood shows up as “Available” when reviewing that tag.

I understand the logic of having indentation blocking actions in sequential projects: Is there a way to change this behavior for non-sequential projects? Thanks!

Sequential vs parallel can be changed on both the project and the parent task of the indented tasks. See the last paragraph of action groups in https://support.omnigroup.com/documentation/omnifocus/mac/2.6/en/projects/.