I’m new to OmniPlan and I’m creating a project for my team (IT solutions), we have a lot of activities that are what I like to call “low effort/high duration tasks” , let me explain to you what I mean.
In real life, these are activities that will take 1 hour of one of my engineers (resources) but it will take more hours to complete, for example, in my company we have a process to generate virtual servers, add all the software and do all the steps that need to be done before they are “Ready”, this activity takes 1 hour of my engineers but 10 hours calendar to actually complete (this process is automated, nothing my engineer needs to do after the process is in progress), if I have to build 100 virtual servers, it takes 3 hours of my engineers (to prepare the system, and to review the templates ) but it will take 8 days of calendar days. I put this activity as an 8 day task but Omniplan then assume the resource is busy for 8 days when this doesn’t meet reality.
what do you think is the best way to present this type of task in OmniPlan?