OF2 Mac Task ordering

I suspect I’m either missing something or after something that isn’t possible…

The attached screenshot shows tasks in a Sequential project which I would like in date order except the repeating task whose next due date is a week away is 1st in line over those due today (now in fact, whoops!)

Has anyone any suggestions, please?

15

If you’re wanting the project to be automatically sorted by due date, it’s true that isn’t possible.

So in this case you would need to either drag the task down to the position you want or select the tasks in your project and go to Organize > Sort Once > By Due Date in the menu.