Hoping to see if someone has an idea for what I am trying to accomplish. I’d like to create a set of tasks with no due date where after the last task is done, it starts again with the first task.
Example: 1,2,3,4,5,1,2,3,4,5,1,2,3,4,5.
Additionally, hoping to be able to complete these tasks in no particular order. In the example above, if I wanted to complete task 2 I could close it, and then tasks 1,3,4,5 would remain. I wouldn’t want to be able to complete task 2 again until I was done with all 5.
You’ll need a container for them, either a parent task or a project. Once you put the tasks inside you can set the parent to “complete with last action”, and make sure it’s parallel (that’s the default). Then in the parent toggle on Repeat and play with the options to figure it out. I would suggest “Defer again after completion” as it will let all 5 actions show up again tomorrow (and you can always modify the defer date!).
Thank you @rosemaryjayne! This seems to get me most of the way there. I went with a project for this and it looks like I have to set it to repeat in order for this to work don’t I. Ideally, I’d like for it to not repeat in case I don’t complete the 1,2,3,4,5 tasks in time. But I think I can make this work. I appreciate you!
Ah! That worked. I didn’t have any items selected. As soon as I ran it, it created the same set of tasks below it. I haven’t used automation much before, would this run in any automated fashion to re-create each set of tasks? Or would I run this at a specific time? I imagine that if I were to complete some tasks and then run this, that it would only duplicate those tasks that are still not complete, correct?
If you set the project to Parallel, then you should be able to complete the tasks in whatever order you wish. It’s only when the last uncompleted task is completed that the project itself completes and then creates the next one.
Actually, @rosemaryjayne’s solution is pretty great. I did set the project to repeat every minute and Defer Until Date and it seems to work exactly as you’d asked. Cool trick.
Ideally I would have those 5 tasks and work towards completing them. After all of them are completed, the new 5 tasks would be generated.
I would also be fine with the next task being generated after I close the first one, but that might be getting into the weeds.
For example: 1,2,3,4,5 are the 5 tasks. Complete #1 and have a new task be created after the last: 2,3,4,5,1. Or just keep 2,3,4,5 until all of them are complete and then generate a new 1,2,3,4,5.
To @Arasmus’ comments, the only challenge to that idea is that the project would repeat based on a time schedule. If I set the time to 1 week and can’t complete all of my tasks, then I wouldnt want the others to pile on. Hope that makes sense!
That’s what I’m saying. While the project is set to repeat (and defer) every minute, that does not happen until you complete the project, which happens only when you complete the last task. Then a new group of tasks immediately appears.
Hey @unlocked2412. I had some more time to think about this and try that code your provided again and this is turning out to provide me exactly what I need. So at this point, I think I am all set.
Thanks to you and the others for helping with this. Great community!