Is there a way to schedule all tasks within a group to start each working day at the beginning of the day?

I basically want to be able to work on project A for two hours every day first thing in the morning. Other projects can be taken care during the rest of the day, but this one is a marathon project, so I need to be sure that I work on it regularly.

You might do best to create an additional resource. Perhaps right now “Anna” works 8 hours per day. Adjust Anna’s work hours to be 6 hours, starting 2 hours later. Now add a new resource, “Anna: marathon” which works those first two hours of the day. Re-assign tasks to this resource as appropriate.