See Resource assigned to each Task in the Tasks view

Is it possible to see the Resource assigned to specific Tasks in the Tasks view.

There doesn’t seem to be a Label option amongst the Task View Options, but maybe there’s another way to do it?

Thanks in advance.

Rob

@ribrob Yes, this is possible! In the View Options, select “Assigned” as a task label.

More information about customizing View Options is available here.

Ah yes - i was looking for “Resources” given that’s what how they’re referred to elsewhere in OmniFocus. :D

Thank you!

dear sir
thanks for some enquiry