Task with multiple enries for partial year to Repeat Yearly

I have some tasks (e.g., lawn mowing) that I only do for certain times of the year (e.g., April to October). I perform this task weekly during this period. I then want to have the same task/project repeat the following year.

I’m getting back to OF from another app that also can’t do this, and I haven’t been able to find a way to do this (v4.9.3) either. I used to have an app (Things, maybe) that could, but I don’t want to keep having to change apps.

Is there a way to accomplish this?

Thanks in advance, Fred

I’m not sure, you’ll have to have a play with this, but since OmniFocus now Supports setting constraints on repeating actions (number of times) could you do the following?

Set a project that repeats annually with a defer date and a due date for the period you want with only one task. You may have to manually complete this project at the end of your mowing season to make it repeat next year

The task should repeat weekly until the last date you want it to.