Tasks completed before anticipated, how to reschedule without shadows

I’ve been completing tasks ahead of schedule and I want omniplan to reflect that without those shadow boxes. How do I update the start time for a schedule and have it move over without showing those “[” shadow boxes" It’s annoying. I understand their purpose but don’t want to see them.

@Rmonson It sounds like you’re referring to task constraints in the Gantt chart. If you’d like to simply hide these, you can do so by unchecking the View > Gantt > Constraints item in the menu bar.

1 Like

That did it! Thanks!