I’m running a few days ahead of schedule in my OmniPlan project, but even though I’ve marked some events as 100% complete, they still get scheduled as future tasks when I level my plan and my project’s end date is never updated.
What can I do to get my project plan to reflect being ahead of schedule? It seems to have support for falling behind schedule, so there must be a good way to handle this. Thanks!