Why does a task inherit its parent group's due date?

Tasks do keep track of their own deadlines independently. But the assumption OmniFocus makes here is that if a group of tasks is due, each task in the group is due by that date as well. (So the effective due date of a task is its own assigned due date or its parent group’s effective due date—whichever comes first.)