How do I set up a 24/7 calendar and resources that are 24/7?

Thanks!

@Johnb You set this up in OmniPlan by customizing your project work schedule and effort conversions. Information about how to do so is available in the following sections of the OmniPlan for Mac manual:

https://support.omnigroup.com/documentation/omniplan/mac/3.6/en/working-in-calendar-view/

https://support.omnigroup.com/documentation/omniplan/mac/3.6/en/using-the-inspectors/#settingeffortunitconversions

Hope this helps!

@Johnb Oops, just noticed that you were asking about OmniPlan for iOS! This functionality is covered in these sections of the OmniPlan for iOS manual:

https://support.omnigroup.com/documentation/omniplan/ios/3.4/en/building-your-first-project/#step9editingtheworkweek