Adding a delay to depanncies in Omniplan

I’m a fairly long time MS Project user and I’m trying to migrate to Omniplan on the Mac (very new with this).

I’m having a problem adding a lag delay to the next task, I wish for a start to start relationship (managed that fine) but with a 2d delay to the second task. The area that seems to be set up for this, next to the prerequisite is greyed out - I have no idea why.

worked it out. Double click on the 0d rather than trying to click the arrows sorted it. Before I did this managed to put the delay in using iOS version.

@Richw I’m glad to hear you figured it out! We have an open bug in our development database on making this functionality more discoverable - I’ll add a note to it that you were tripped up by the current UI as well.