Most of my team works week days and weekends are excluded from their working hours in the resources.
However one team does work weekends. I have their hours set to weekends in the resources menu as well as weekdays.
Now, in the timeline the weekend crew is not appearing. A weekend project from Saturday to Monday counts as one day duration.