Daily scheduling still includes time data [fixed]

I’ve set my project for daily scheduling and removed all time related data but when I try to move the task on gantt chart by dragging it further it still moves by hours. How can I enforce movement by days?

Fix was actually pretty simple, but not as straightforward.
All you need to do is to hold shift while moving the task. It’s a pitty I still need to do this even though the whole project it set for daily scheduling.