Delay tasks until whole task can be completed in a single day

I have situations where I need to schedule someone to go out on a delivery. The delivery will take 4 hours, so I need omniplan to delay the task until it can be completed all at once (on the same day). I keep running into the situation where omni plan starts this task in the afternoon for 2 hours and tries to finish it the next morning (remaining 2 hours).

How do I tell omniplan I need a task to start and be completed in a single day? I want to delay the task until enough time is available. Or this just something I have to do manually?

Thanks!

@justin522 Currently, the only way to set this up in OmniPlan is by changing your project’s granularity to “Daily.” More information about scheduling granularity is available in this subsection of the OmniPlan manual.