I have situations where I need to schedule someone to go out on a delivery. The delivery will take 4 hours, so I need omniplan to delay the task until it can be completed all at once (on the same day). I keep running into the situation where omni plan starts this task in the afternoon for 2 hours and tries to finish it the next morning (remaining 2 hours).
How do I tell omniplan I need a task to start and be completed in a single day? I want to delay the task until enough time is available. Or this just something I have to do manually?