I have a large project that has 3 major phases. Each phase has several groups, tasks and milestones.
For now I just need to find out the critical path for the first phase. However, when I click the critical path button it only shows me the critical path for the whole project which is not very accurate.
Is there a way to show the critical path of only the selected group?
@Enrique It sounds like you’re looking to enable the critical path to a specific milestone within your project. This can be done by selecting the milestone in the Milestones Inspector and checking the “Show critical path to this milestone” option. More information about working with critical paths to milestones is available in these sections of our manual: