I like the idea of working with subtasks as a way of using checklists to double-check some mid-sized tasks. However, I’m struggling to get it to work with other perspectives. They seem to always be treated as discrete tasks. I’d like to keep the task hierarchy when in other perspectives.
Is there any way to have the main task always carry its subtasks with it when in other perspectives?
If you ‘group and sort’ entire projects in the perspective, the hierarchy is shown. That’s the only way that I know of, but of course might not be desirable for other reasons.