Microsoft project versus Omniplan

Hello,

I’m moving from Microsoft project to Omniplan.
Have Omniplan the functionalities below:
. Project status date;
. Inactivate tasks;
. Recurrence tasks;
. Custom fields with possibility to associate formulas and icons;

King regards,
João Seiça

I believe OmniPlan’s “Set Current Editing Date” feature functions similarly to Microsoft Project’s project status date. OmniPlan does not currently support inactive or reoccurring tasks, and at this point in time custom fields only support text input.

Hope this helps!