I often have resources that have availability change during the workflow of a task. For example, Resource A is 25% for the first 6 months of the task, but then goes to some different percentage after that time point (for example 75% or 100%). Is there a way to do this in omniplan?
Also, is there a way to display the assignment percentage on the resource timeline?
@pmpjoe This functionality doesn’t currently exist in OmniPlan, sorry! Any change in resource availability over the course of a project would need to be handled by manually assigning a resource at the appropriate % to separate tasks over the course of the project.
If you’d find it useful to be able to assign variable resource availability, please email our Support team a feature request! omniplan@omnigroup.com