Schedule portion of project to specified date

I recognize we can schedule a project start or end date. But I’ve got a project that has a significant preparation and follow up stage, while the field stage in the middle of the project must happen at a specific time. Obviously I can do the math and set the project to the appropriate date. But is there some way I’m missing to schedule the middle of a project to a date and let the rest of the project schedule itself accordingly?