Sharing a resource (a workstation)

Hello,

I want to:

Assign task 1 to person 1
Assign task 2 to person 2

And

Assign Resource 1 to both tasks (a workstation of which I have only one and it’s needed for the progress on each task)

And have Omni automatically assign times to work on person 1 and person 2 according to their schedule, sharing the resource in a way so that only one person at a time is using it.

How?

@icefire It sounds like adding an Equipment resource to your project should help accomplish what you’re looking to do! Information about using different types of resources in OmniPlan is available here:
https://support.omnigroup.com/documentation/omniplan/mac/3.10/en/working-in-resource-view/#resource-types