Use only 1 resource from Group

Hello, guys!

I’ve hit a problem I want to share - maybe someone knows a solution.

So, I have a pack of resources (2 ppl) in group with 50% load each and I assign them to a bunch of tasks.

As a result of automatic leveling I get this picture:

But due to some internal reasons it’s impossible to do our tasks in team, so I want to know, can Omniplan assign only 1 resource from group to the task, but increase the task duration? In this case Task 1 should be assigned to Res 1 and take from 6 to 7 June, Task 2 to Res 2 with same duration and so on.

Many thanks in advance.

@Kawaii I think setting your group assignment to 50% and re-leveling should do the trick!